Project Progress completed in December 2017

  • Framing for decks commenced and completed
  • Timber decking installation on all residences
  • Communal entry path formwork commenced
  • Stairwell hand rails installed
  • Stone bench tops installed in all bathrooms and kitchens
  • Walk in robe joinery installed
  • External power points and lighting installed
  • Shower screens installed in residences
  • Ducted vents installed in kitchens and throughout

19876078 10215366905344663 240637774 O
25551347 10215366906464691 61978323 O
25551580 10215366905544668 440077753 O
25590605 10215366906024680 1448822072 O

Project Progress completed in November 2017

  • Boundary fence removed and replaced
  • Bathroom tiling commeced on all residences
  • Basement garage ceiling plastering completed
  • Basement garage electrical fitout commenced
  • Under stair storage doors installed
  • Kitchen joinery delivered on site and installation commenced 

Base
Bathr
Door
Fenc
Kitche

Project Progress completed in August 2017

  • External Cladding works begun on all dwellings on level 2
  • Scaffolding installed.
  • Electrical rough in underway and plumbing rough in completed
  • Insulation sheeting installed internally
  • Gas meters installed

20170831 150532
20170831 150608
20170831 150657
20170831 150725
20170831 150840

Project Progress completed in September 2017

  • External Cladding works complete on level 2
  • Mechanical rough in completed
  • Roofing works completed
  • Internal plastering commencing 

 

20171026 111309
20171026 111412
20171026 111440

Project Progress completed in July 2017:

  • Brick feature walls completed on ground floor.
  • Roof tiling completed. 
  • Water and Electrical services installed.
  • Cellestial window timber framing completed.
  • Garage structure completed.

20524494 10159256119705790 988237062 O
20526510 10159256119080790 869067001 N
20527425 10159256119095790 1308597034 N
20561940 10159256118915790 1546607032 N
20614301 10159256118980790 1557973381 N